News

City Water and Light of Jonesboro Board Approves Rate Increases, Bonds to Fund New Plant Construction

City Water and Light of Jonesboro Board Approves Rate Increases, Bonds to Fund New Plant Construction

Photo: Saga Communications/Rachel Rudd


Jonesboro, AR – Jonesboro Right Now – The City Water and Light (CWL) of Jonesboro board on Tuesday unanimously approved a resolution to increase electric rates, as well as a resolution to secure bond financing to fund building a new gas plant.

The electric rate increases will be enacted in two phases, with the first phase beginning Jan. 1, 2027, and the second beginning Jan. 1. 2028. A third rate adjustment, which would go into effect Jan. 1, 2029, will be considered by the board separately after financial review in 2028.

The approximate rate increases for each customer class are listed below:

Customer Class:Phase 1 (2027):Phase 2 (2028):
Residential Service5.3%5.5%
Commercial Service5.9%5.5%
Industrial Service3.5%4.4%
Security Light Service5.8%5.8%

“We are starting from a very good position. We haven’t had a base rate adjustment since 1984, and our electric rates are about 2/3 of averages across the country, and we’re among the lowest in the state and the region,” said CWL manager Jake Rice during the meeting. “We’re in a very good position to adjust rates and hopefully avoid significant impacts to our customers.”

According to a press release from CWL, individual bill impacts will vary based on customers’ kilowatt-hour (kWh) use. For example, a residential customer using 1,250 kWh per month would see a bill increase of about $5.56 per month in 2027, and an additional $3.63 in 2028. This would bring this customer’s electric portion of their bill to $111.47 by 2028.

ADD US ON GOOGLE NEWS: Click here to see more local news from Jonesboro Right Now

The rate increases are in part to help fund the construction of a new energy plant, of which CWL will have about 15.4% ownership. CWL, along with Arkansas Electric Cooperative Corporation and others, will be partnering to the new Independence Combined Cycle Natural Gas Plant (CCGP) at what is currently the Independence Coal Plant near Newark.

 The CCGP plant will be a natural gas plant that uses exhaust heat to generate additional power with no extra fuel or emissions. CWL has previously said this new plant will generate power more cheaply than coal plants and produce fewer emissions.

The plant will cost $2.6 billion in total, according to a report from Construction Review.

CWL’s cost share of the project will be $350 million to be paid over five years. About $100 million will be paid for through reserves, while the remaining $250 million will be financed through bonds. CWL officials said these bonds would produce additional revenue needed to fund the plant, as well as maintain financial metrics related to the utility district’s bond rating.

| READ MORE: CWL of Jonesboro Celebrates 120 Years; Shares Future Plans

The board on Tuesday unanimously approved issuing bonds up to $100 million. It approved $60 million worth of bonds in 2025, and additional bond issuances of $65 million and $30 million are expected in 2028 and 2029, respectively.

The CCGP construction follows a 2021 legal settlement with the Sierra Club and the National Parks Association, which was approved by the Arkansas Department of Environmental Quality and the Environmental Protection Agency, to cease coal use at the Independence Plant.

The lawsuit concerning the settlement was filed in 2018 after environmental groups accused Entergy Arkansas of violating the Clean Air Act, according to reporting from the Arkansas Democrat-Gazette.

Per the settlement, the existing coal plant can continue its operations through 2030 without installing emissions controls. CWL has previously said installing these controls would cost nearly $200 million, and the plant would need to run for another 30 years to recoup costs.

The CCGP is expected to enter service on Jan. 1, 2031, right after the Independence Coal Plant ceases operation.

Prior to the board approving the rate adjustments, energy marketing administrator Slade Mitchell told board members that CWL had already mailed out information in the previous weeks to inform customers. He noted that CWL officials had met in-person with large industrial partners and various civic groups to provide more information about the increases.

With the board’s approval, another mailer, he said, will be sent out Sept. 8 to provide details on the board’s decision and the rate increases. He added that on Aug. 26, a microsite explaining the increases will launch. It went live Wednesday afternoon.

It contains information on why base electric rates are increasing, frequently asked questions, and allows customers to see what their individual rate increases will be. It can be accessed here.

Social media updates announcing the changes will also be posted, he said.

“Forecasts are showing that when you look at what it will cost us to serve our customers off the market for capacity and energy, we believe [the CCGP] will, over its life, save our customers hundreds of millions of dollars,” Rice said. “Our right to reuse the generator interconnection, that independence has placed our customers in a great position to get this plan built in a timely manner, and we believe well below the going market value for these types of plants.”

Update Aug. 26: A link to the microsite explaining the rate increases was added to this article.

| DAILY BRIEF: Sign up for the Jonesboro Right Now Daily Brief Newsletter

This Week in Jonesboro

Music News

5 days ago in Entertainment, Music

Dolly Parton estate announces 2-day festival ‘Dollyfest’ to celebrate her legacy

Dolly Parton is not done yet. The estate behind the icon, who died of cancer last week at age 80, has announced Dollyfest, a two-day festival to be held in Nashville and London across two consecutive weekends in 2027.

2 weeks ago in Entertainment, Music

Australia’s music industry bans AI-generated tracks from official charts

Australia's recorded music industry will bar tracks wholly generated by artificial intelligence from official charts as burgeoning generative technologies threaten artists' livelihoods, a representative said on Tuesday.

2 weeks ago in Entertainment, Music

After losing a friend and writing ‘Say So,’ Dan + Shay are back with the autobiographical ‘Young’

The lead single from Grammy Award-winning duo Dan + Shay's forthcoming album "Young" is a hard pivot from the wedding songs that make up so much of the country pair's discography.

3 weeks ago in Entertainment, Music

Frank Beard, Rock & Roll Hall of Fame drummer of boogie-rock trio ZZ Top, dies at 77

Frank Beard, the drummer for the Texas boogie-rock trio ZZ Top who kept the tempo for the band's biggest hits like "Sharp Dressed Man," "Legs" and "Gimme All Your Lovin,'" has died. He was 77.

3 weeks ago in Entertainment, Music

Madonna leads 2026 MTV Video Music Awards nominations, followed by Taylor Swift

Madonna leads the 2026 MTV Video Music Award nominations, the network announced Tuesday. The pop superstar has been nominated in every decade of her musical career. She has 19 competitive MTV VMA wins and in 1986 became the first solo female artist to receive the Video Vanguard Award.